Shop Floor Control - Copy Shop Floor CalendarFunctionUse this task to copy a shop floor calendar from one operation to another. Copies can be made to multiple operations at one time.
=>To access this menu... Select the Copy Shop Floor Calendar from the Inquiry and Maintenance menu. Copy Shop Floor Calendar
About the Fields
In the Operation Code field...
An operation code is required with a scheduled calendar. If there is no calendar currently scheduled for the selected operation code, you will remain in the field.
In the First/Last Scheduled Date field... Display only. Shows the first/last date of the currently selected operation code’s scheduled calendar.
In the Date to copy from field...
In the Date to copy through field...
In the lower section of the form, use the checkboxes to select the operation code(s) to create the new calendar.
When finished making entries to the fields…
______________________________________________________________________________________ Copyright BASIS International Ltd. AddonSoftware® and Barista® Application Framework are registered trademarks. |